Plans for 320 apartments across two towers in Stones Corner have moved through months of detailed assessment, with new wind and noise studies among the latest documents lodged as Brisbane City Council considers the development.
The proposal at 71–85 Cleveland Street was in its decision period during September, several months after Council issued a detailed information request covering everything from landscaping and parking to stormwater, noise and the proposed building height.
Recent documents show the assessment continued into September. Council agreed to extend the decision period to 25 September after the applicant sought additional time to progress sustainability, acoustic and wind matters.
As at 26 September, however, the material reviewed by Greenslopes News does not establish that a final development approval has been issued.
Months of Questions and Revised Material
When Greenslopes News first reported on the application in May, the proposal involved two towers of about 20 storeys containing 320 apartments.
Council’s assessment subsequently produced an information request on 5 June, which sought further information or revisions across 12 matters.
Among them was the podium’s proposed 86.9 per cent site cover, above the 75 per cent maximum identified in the Eastern Corridor neighbourhood plan code. Council sought reduced site cover and improvements to frontage landscaping, boundary buffers and deep planting areas.
Council also questioned the balance between car and bicycle parking. Its information request said resident car parking was proposed at 30 per cent above the relevant acceptable outcome while resident and visitor bicycle parking was 50 per cent below it.
Other matters included stormwater discharge, waste servicing, street trees and powerlines, noise and the treatment of the upper communal level as a rooftop garden.
By late August, the application record included amended noise material and revised landscape plans. September correspondence indicates Council and the applicant had progressed to discussing draft conditions — a significant step forward from the information-request stage, although not itself an approval.
Wind Study Tests the Towers From Street to Rooftop
A wind assessment dated 15 September examined pedestrian conditions around the development and on its elevated outdoor areas.
MEL Consultants tested a 1:400 scale model of the proposed development, described in the report as Vivo Apartments, against a model incorporating surrounding buildings and topography extending at least 300 metres from the site. The testing considered winds from all directions.
The consultant found no exceedances of its pedestrian safety criterion at the ground or upper levels. Some locations were above the more stringent walking-comfort criterion, although several of those locations were already above that benchmark under existing conditions.
The neighbouring petrol station, car parks and private open spaces would also become windier at several test locations, according to the study, but remained within the safety criterion.
At Level 1, two private corner terraces were slightly above the walking-comfort benchmark for one wind direction. Higher private terraces tested on Levels 4, 10 and 17 achieved the walking criterion or better, while two rooftop locations were slightly above it for particular wind directions. Taller balustrades were identified as one option for improving conditions in some of those areas.

The Proposal Remains at 320 Apartments
The latest technical material continues to describe a two-tower, 20-storey development containing 320 apartments.
An amended noise assessment issued in August also followed Council’s earlier request for further work. It included additional measurements and assessment of the nearby service station, with the consultant recommending acoustic treatments for parts of the development.
On 9 September, the applicant sought another 10 business days in the decision period to continue working through sustainability, acoustic and wind matters. Council agreed to an extension until 25 September and asked whether the applicant’s response to draft conditions was also expected.
That exchange shows how far the application has progressed since May, but there is an important distinction: draft conditions are not development approval.
For Stones Corner, the next definitive milestone will be Council’s formal decision on the application.
Published 25-September-2026